Stage 1
Progress
81%
Construction: Underway
Anticipated titles due: November
Construction progress
Stage 1 works are complete, with testing and commissioning now well underway. Statement of Compliance is on track for November, with titles expected shortly thereafter.
Overall Construction
81%
Site Prep & Earthworks
100%
Sewer & Drainage
100%
Water
100%
Roads & Pavements
100%
Electrical & Communications
100%
Footpaths & Finishing
100%
Statement of Compliance
50%
Registration of Titles
0%
Stage 2
Progress
85%
Construction: Underway
Anticipated titles due: QX XXXX
Construction progress
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nunc mollis rhoncus justo, ac pulvinar turpis tincidunt elementum. Fusce euismod libero sit amet est suscipit consequat.
Design GuidelinesPlan of SubdivisionEngineering Plan
Construction
41%
Site establishment
100%
Earthworks
62%
Drainage Works
49%
Subgrade
27%
Electrical
12%
Footpaths
0%
Registration
44%
Statement of Compliance
100%
Plans of Subdivision
33%
Settlements
12%
Stage 3
Progress
85%
Construction: Underway
Anticipated titles due: QX XXXX
Construction progress
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nunc mollis rhoncus justo, ac pulvinar turpis tincidunt elementum. Fusce euismod libero sit amet est suscipit consequat.
Design GuidelinesPlan of SubdivisionEngineering Plan
Construction
41%
Site establishment
100%
Earthworks
62%
Drainage Works
49%
Subgrade
27%
Electrical
12%
Footpaths
0%
Registration
44%
Statement of Compliance
100%
Plans of Subdivision
33%
Settlements
12%